Procter & Gamble | Seismic Retrofit

Procter & Gamble | Seismic Retrofit


CLIENT

Procter & Gamble

LOCATION

St. Louis, Missouri

SIZE

60,000 sf

PROJECT SIZE

$2 million

MARKET

AWARDS

PROJECT NOTES

Tarlton completed a seismic retrofit that brought a four-story, 60,000 sf structure up to code requirements. As the project began, the team became aware of a substantial void in a 500-foot-long stone foundation wall. Working with structural engineering consultants, Tarlton devised and successfully carried out a unique solution to restore the structural integrity of the six-foot-tall wall.

The project encompassed excavation, backfill and offsite disposal of excess material, installation of new concrete foundations, removal and replacement of columns, and the application and installation of shotcrete, plus welded wire fabric (WWF) reinforcement through bolts, rebar, angles, ties, lag screws and other strengthening materials.

The team also relocated a sump pump and associated piping, demolished an elevator and replaced the roof (under separate contract). Critical computer equipment in the basement was protected throughout the building restoration and upgrade.

Featured Industrial Projects

See All Industrial Projects

    • Industrial

    Hartmann North America | Manufacturing & Distribution Facility Renovation/Expansion

    Rolla, Missouri

    • Civil

    Mechanical Dynamics & Analysis | High Speed Balance Facility

    St. Louis, Missouri

    • Industrial

    Prairie State Generating Company | Railcar Unloading and Material Handling System

    Marissa, Illinois